Pittsburgh & Ohio Valley Railway

Neville Island's steel-plant railroad, 1899–1994 · October 2026

From 1899 to January 31, 1994, the Pittsburgh & Ohio Valley Railway (P&OV) switched the east end of Neville Island: first as American Steel & Wire's plant railroad, last as Shenango's. HART Railroad's Pittsburgh & Chartiers Valley Division is its successor, and this page collects what is known about the P&OV's jobs, track names, moves, and equipment.

Nearly everything here comes from the @pittsburghohiovalleyrailroad Tumblr blog kept by Mark Connolly, a P&OV trainman and engineer from 1977 to 1991. Each "p." reference is a page of the blog's PDF export and links to the original post, where the photos are. The crew and their stories are in Voices of the P&OV.

P&OV at a glance

The P&OV switched Neville Island for 94 years, from 1899 to 1994. It began as American Steel & Wire's plant railroad and ended as Shenango's. In 1923 it had 2.04 miles of main track and connected with the P&LE and the PC&Y.

DateEventSource
Jan 31, 1994P&OV ceases to exist as far as the Railroad Retirement Board is concernedp.125
Oct 3, 1990"The end was near" — last casts at Shenango B furnace around this timep.49, p.71, p.87
1980sCrews in UTU Local 150; merger issues with the P&LE and CSXp.56
1977Loco #5 "a real dog… just wore out"p.124
1962Shenango coke works begins its 54-year run (56 ovens, closed Jan 2016)p.20
1950sGeorge B. Moser is P&OV president and also PC&Y trainmaster at McKees Rocksp.101
1940sPhoto of a P&OV crewp.113
Jul 1939Hunter Steel sells its Neville plant to Shenangop.83, p.107
1928Davison Coke & Iron buys the upstream-end blast furnace from U.S. Steelp.116
1923Owned by U.S. Steel: 2.04 mi, general freight, connects with P&LE and PC&Y, and through the PC&Y with the Pennsylvania System; no merchandise freight facilitiesp.120, p.142
1920Pennsylvania PUC decision on P&OV ratesp.113
Sep 20, 1918 – Jul 1, 1919Taken over by Army Ordnance for the planned island munitions plantp.136
Jun 30, 1919ICC valuation: 2.039 mi main track, 4.033 mi yard and sidings, 3 steam switchers, 1 freight carp.119, p.137
Nov 19165.13 mi sold back to American Steel & Wire; P&OV buys the land under the remaining 6.07 mip.136
1915–1916"Not much of a money maker"p.18
1914ICC report lists the P&OV under American Steel & Wire / Carnegie Steelp.132
Feb 1900 – Oct 1902About 11.2 mi of track built on American Steel & Wire landp.136
Dec 5, 1899Incorporated in Pennsylvania; controlled by American Steel & Wirep.119, p.136

The blog does not say when control passed from U.S. Steel to Shenango. By the 1960s P&OV crews were in the Shenango pension plan (p.11, p.119).

The jobs

The only place the blog lists every job is Mark Connolly's answer to modeler Steve Raque, who asked what the numbers meant and what each job did (p.2). Mark said the number stood for the shift and the duty. There were five numbered jobs and an EXTRA. Two were daylight jobs with different work. The others were the second trick, the midnight trick, and a relief job that covered the days those jobs had off. Photo captions supply the moves.

JobShiftWhen it worked
#1057:00 a.m. – 3:30 p.m.Monday–Friday. Off Saturday and Sunday.
#110DaylightMonday–Friday. Off Saturday and Sunday.
#2054:00 p.m. – midnightOff Wednesday and Thursday. East and west as required.
#305Midnight – 7:00 a.m.Off Monday and Tuesday. East and west.
#115The shift changes with the dayMonday and Tuesday midnight, Wednesday second trick, Saturday and Sunday daylight.
EXTRAAs calledWhen the plant was super busy, or the scale was down.

Read across the week, the relief job sits in the holes Mark named. Monday and Tuesday midnight, #115 covers the nights #305 has off. Wednesday afternoon, it covers the second trick #205 has off. Saturday and Sunday, it is the daylight crew, when both #105 and #110 are off. The blog does not say who worked Thursday's second trick.

A trainmaster wrote the switching orders for the crew on duty (p.76). Weighing belonged to the yard clerks and the trainmasters, at the Toledo scale in the yard office (p.95).

#105, the ore job

This was the job men wanted. Daylight, Monday through Friday, 7:00 a.m. to 3:30 p.m., mostly in the West Yard. Mark called it the clean end of the plant, and the senior men held it (p.2, p.105).

The work was iron ore for Shenango. The crew shoved ten-car drags off the South Runner to the car dumper. The brakeman was supposed to ride the fifth car (p.84). At the dumper the hoppers were turned on E2, and a car rider rode the empties back down the hill, braking by hand (p.39, p.44). Captions show the drag coming up to the coke yard switch, and the engine spotted for fuel in the South Yard between trips (p.114, p.58).

Coffee belonged to the day. Don Amber and Bob Paulin drank it near the coke plant lead, in the green P&OV hats (p.105). After a drag to the dumper, around 10:00 or 10:30, the crew stopped at the millwrights on the furnace lead and brought coffee back for the yard office (p.57). An early quit at the end of the shift was something to smile about (p.75). A crew coming on duty would sometimes step onto the footboard, relieve the engineer, and weigh the cars or take one more drag, so the crew going home could leave a little early (p.55).

In the early 1980s the engine on this job was SW9 #4 (p.37). Nick Niapas conducted it, and sometimes the furnace job as well (p.9).

#110, the furnace job

The other daylight job, Monday through Friday, on the east end. Mark called it a graphite and coke dust area. It served the two blast furnaces, the pig machine, and the coke plant (p.2). John Doubt worked it often enough that a caption names it the Furnace Job (p.139, p.57).

Furnace coke was pulled from the Shenango coke plant, weighed on the yard-office scale, and taken to F1 at the blast furnace. The furnace job lined the crossing for that move, and the conductor rode the lead hopper (p.130, p.120, p.55). While B furnace finished a cast, the crew waited at the rear of the furnace runner, short of the bumping block (p.14).

The ladle, pig, and barge moves below are described on this east-end territory. The captions do not repeat the job number on every one of them.

Hot metal moved in ladles, switched two at a time out of the ladle house. The crew had to watch the weight or the cut would reach the quench car at the battery (p.14). Ladles were heated on E9 before they were spotted, and switched from E6 to E4 because they were rarely in the order the furnace wanted (p.77, p.91). Mark's split was one to the foundry, one to the pig machine, and one for recast (p.138). Iron for the Shenango foundry, at the other end of the island, left by the pig-yard lead at the Gulf Crossing. The PC&Y interchange was just west of that crossing, and crews bled the ladles and gons there (p.138, p.105).

At the A-furnace pig machine, bars dropped into gondolas two loads at a time. The crew pulled those two loads and kept the safety car clear of the East Runner (p.110). Loads of pig iron were spotted on E1 for the barge, on a steep grade (p.95). Empty pig gons were picked up in the East Yard, near West View Water (p.92).

#115, the relief job

Mark lists five shifts, and the trick changes with the day: Monday and Tuesday midnight, Wednesday on the second trick, Saturday and Sunday daylight (p.2). It covered the rest days of the other jobs, east or west as that day's work required.

In August 1979 Larry Obusek had SW9 #6 on this job, with Joe Adamcik on the front of the engine, about to roll across the scale. Mark thought the scale had been thrown red (p.126). Elmer Picard worked the relief job as well as the steady second-trick job (p.67).

#205, second trick

4:00 p.m. to midnight, off Wednesday and Thursday, working the east end and the west end as the plant required (p.2). Elmer Picard held it as a steady job. He came to work in a sport coat and tie, and Mark said he looked like he owned the place when he filled out his time sheet (p.67). The blog gives this trick no separate list of moves.

#305, the midnight job

Midnight to 7:00 a.m., off Monday and Tuesday, east and west (p.2). The one task a caption names is the last one. The crew spotted the engine on S9 for sand and went home. In a 1980 photo that engine is #3, just west of the scale, with the track gang loading sand by the bucket (p.99).

EXTRA

An extra was called when the plant was super busy, or when the scale was down (p.2). The men who covered it were the extra board, and a call could be a long time coming. Scott Morrison was third out most of the time (p.72). Asked in 1988 why railroad employees were not guaranteed 40 hours a week, John Iwanonkiw answered that they had spent those years on the extra board (p.62).

The two east-end furnaces

The two furnaces next to the coke plant are Shenango blast furnaces A and B. They are the iron works on the east end of the island. The Shenango-Penn foundry is a different plant, about two miles west, at 3100 Grand Avenue. Stanley Quick, who spent 38 years at Shenango, put the foundry where the main road bends, a small works compared with the coke plant, and connected to it by rail.

Ore and furnace coke went to A and B. The foundry took the hot iron those furnaces cast, in ladles. A P&OV engine worked that ladle job at the foundry. The PC&Y interchange, just west of the Gulf Crossing, is where ladles and gons changed roads on the way off the east-end plant.

What the railroad brought in

Iron ore came onto the island over the PC&Y. A PC&Y man recalled hauling it out of Scully Yard. On the island, #105 shoved it from the West Yard to the Shenango car dumper in ten-car drags. A 1980 photo taken from the dumper looks back across the ore yard with both furnaces standing behind it (p.38). The dumper trestle also looked out on a stockyard of ore, coal, dolomite, and coke (p.108).

Furnace coke moved the other way. #110 pulled it from the battery, weighed it at the yard-office scale, and took it to track F1 at the blast furnace. The furnace job lined the crossing for that move.

Where A and B sat

The captions give a view, not a survey.

The Furnace Runner runs east past the pig machine at A furnace and ends at a bumping block. Crews waited there while B finished a cast (p.14, p.120). When A was being cut up for scrap, the gons sat on the old pig-iron holding track, the East Runner was to the right, and B was still standing in the background (p.60). A is the near furnace, the one with the pig machine. B is the one beyond it.

Hot metal left the ladle house two ladles at a time. Mark's split was one to the foundry, one to the pig machine, and one for recast. At A's pig machine the bars dropped into gondolas two loads at a time, and the loads were spotted on E1 for the barge.

How the pair got there, and when it left

The first stack is the American Steel & Wire furnace of about 1900. The company history Mark posted says that when Davison bought it from U.S. Steel it was a 550-ton-a-day furnace on 159 acres at the upstream end of the island. Davison enlarged it, built the coke plant to feed it, and built the cement plant to use the slag. The pig iron was sold to foundries in the Pittsburgh district (p.116).

In 1951 Pittsburgh Coke & Chemical raised money to double pig-iron output from 300,000 to 600,000 net tons a year. That program is the second furnace, which EPA dates to about 1952. In 1958 the company spent about $2.5 million to adapt one of the two furnaces to make ferromanganese and spiegeleisen as well as pig iron. Half of that money was a gas-cleaning system. The published note does not say whether the converted furnace was A or B.

Shenango Furnace bought the coke-and-iron works in 1962 and kept both stacks. A came down first and stayed in place while B kept running. Stanley Quick describes the shutdowns as staged. Mark's scrap photo is the same moment: A going out, B still up. The last casts at B were around 1990. The foundry closed in January 1990. The iron department closed over 1990–91, and the pig machine was sold and rebuilt at Sparrows Point. After that the east end was a coke plant. HART's Shenango map is that later plant: tracks K-1 and K-2 at the coke works. The ore dumper, furnaces A and B, the pig machine, the ladle house, and the ladle run to the foundry are not on it.

The longer corporate history is in Neville Island coke, cement, and chemical history.

Track and place names

The P&OV's three yards (West, South and East) already share their names with HART's station maps. Its scale also sat just east of S9 at the yard office, which matches HART's scale on the South Yard west lead. Track numbers seem to carry a yard prefix (E = East, S = South, F = furnace; C is unclear). That is inferred from the captions, not stated.

Yards and buildings

NameWhat it wasSource
West YardOre yard worked by #105; the Gulf Crossing and the PC&Y interchange were at its edgep.2, p.25, p.114, p.138
South YardLocomotive fuel spot; PC&C gas holder visible behind itp.34, p.58, p.104, p.113, p.127
East YardScrap yard, ladle tracks, empty pig iron gons near West View Waterp.33, p.77, p.92
Yard office / scale houseOffice with a Toledo track scale; cars weighed here, crews filled out time sheets, gin games in the back roomp.42, p.89, p.95, p.120
Main crossingRoad crossing; looking west from it: yard office on the left, then South Yard and West Yardp.115
Gulf CrossingCrossing at the pig yard lead switch; the Gulf terminal was nearbyp.25, p.74, p.91, p.138
Track gang yard / gandydancer shedMaintenance-of-way base near the west end of S1; crews stopped there for coffeep.74, p.100, p.135
Crew roomLockers; first microwavep.129, p.138

Running tracks

NameWhat it wasSource
East Runner ("East Runner Main")Main east–west track along the back channel past Marquette Cement and A furnacep.49, p.60, p.110, p.141
South RunnerTrack where ore drags were made up; ran past the track gang yardp.74, p.84, p.135
North RunnerVisible with the South Runner and the interchange switch in 1962p.135
Furnace RunnerRan east past the A furnace pig machine, with a bumping block at the rearp.14, p.120
Furnace leadLead to the furnaces; millwrights' coffee stopp.57
Coke plant leadLead to the coke plantp.105
Coke yard switchSwitch approached by ore drags heading to the dumperp.114
Pig yard leadLead switch at the Gulf Crossing into the pig iron yardp.91, p.138

Numbered tracks and switches

NameWhat it wasSource
E1Pig iron loads spotted for barge; "steep grade and lots of weight"p.95
E2Car dumper track; car riders worked the dumper side and rode strings down the hillp.39, p.44, p.108
E4 / E6Ladle tracks; ladles switched from E6 to E4 to spot for furnace castingp.91
E5Next to the yard office; a caboose once sat therep.137
E9Ladle heat track in the East Yard scrap yard; ladles had to be very hot before spotting. In Jan 1984 the track spread from the heatp.77
S1South Yard track; its west end was near the gandydancer shedp.100
S9Just west of the scale; sand spot (sand loaded by bucket) and run-around for outbound tank carsp.90, p.99
F1Furnace coke delivery track for the Shenango blast furnacep.130
C9 switchA switch that froze solid at −10 °F in the early 1980sp.142

Industry and interchange spots

NameWhat it wasSource
Y Interchange (PC&Y interchange)Interchange with the PC&Y just west of the Gulf Crossing; ladles and gons exchanged herep.35, p.68, p.88, p.101, p.105, p.138
Car dumper and trestleShenango ore unloading: dumper, transfer car, high lift, ore pit; stockyard of ore, coal, dolomite and cokep.38, p.40, p.41, p.87, p.108
Ladle house ("the house")Where hot-metal ladles were stored and switched, two at a timep.14, p.87, p.108
A furnace pig machineCast pig iron into gondolas, two loads at a timep.42, p.110
A and B furnacesShenango blast furnaces; A dismantled first, B's last casts around 1990p.38, p.58, p.60, p.71
Coke battery / quench carShenango coke plant; quench car moved hot coke from the batteryp.14, p.93, p.109
Shenango foundryAt "the other end of the island"; received hot iron by ladlep.3, p.138
Chemical plantLikely Pittsburgh Coke & Chemical; shipped tank cars (CSX later served it)p.9, p.78, p.90
StuckiReceived a boxcarp.22
Marquette CementTower next to the East Runner on the back channelp.141

Typical moves

Almost every P&OV car crossed the yard office scale. The traffic was mostly Shenango's own: ore in, hot metal and pig iron around the island, and coke from the battery to the furnace. The job write-ups above tell that work by crew. This table is the same traffic, one row per move.

FlowRoute and handlingJobSource
Furnace cokePulled from the Shenango coke plant, weighed at the yard office scale, then taken to F1 at the blast furnace. Crews coming on duty sometimes relieved the engineer to weigh cars or take a drag#110p.55, p.120, p.130
WeighingCars rolled across the Toledo scale and the clerk read the weight as soon as they cleared ("bam, the buzzer was off"). The scale could be "thrown red" to stop a move; when it was down, an EXTRA was calledAllp.95, p.126, p.2
Chemical tank carsOutbound tank cars from the chemical plant; engine runs around them on S9Anyp.90
InterchangeCars and empty ladles swapped with the PC&Y at the Y Interchange; gons "bled" (air released) there before moving#110, #205p.88, p.101, p.105, p.138
Boxcar to StuckiOccasional boxcar for the Stucki plantAnyp.22
Ore dragsLoaded ore hoppers shoved from the South Runner in 10-car drags up to the car dumper. A car rider then rode the empties down the hill in strings, braking by hand#105p.2, p.40, p.44, p.84
Hot metalB furnace cast into ladles spotted in order (switched E6 to E4). Ladles left "the house" two at a time, split "one to the foundry, one to the pig machine, one for recast"; empties returned via the Y Interchange. Ladles were heated on E9 first#110p.14, p.77, p.91, p.138
Pig ironPig machine at A furnace loaded gons two at a time (keeping the safety car clear of the East Runner); loads spotted on E1 for barge; empties picked up in East Yard#110p.92, p.95, p.110
ScrapGons spotted to load out A furnace as it was dismantledAnyp.58, p.60
ServicingFuel at South Yard; sand loaded by bucket on S9; water added by hand at the scale houseAnyp.34, p.72, p.99

Locomotives, equipment, and crew roles

By the late 1970s the P&OV ran green diesel switchers numbered 3 to 6, with SW9s #4 and #6 doing most of the work. Heavy repairs were done at the P&LE shops in McKees Rocks.

UnitTypeNotesSource
#3Switcher (model not stated)Fresh paint photo in East Yard with rerailers, armrests and awnings; scrapped at McDonald, Ohiop.33, p.75, p.124, p.132
#4SW9Main daylight engine on #105 in the 1980s; fueled at South Yard; repaired at the P&LEp.25, p.37, p.55, p.114, p.121
#5Switcher (model not stated)"A real dog in 1977. No power and just wore out"; repaired at the P&LE McKees Rocks shopp.102, p.121, p.124
#6SW9Worked #115 in 1979; East Yard 1980; repaired at the P&LE engine shopp.92, p.101, p.113, p.126
1919 roster3 steam switchers, 1 freight carICC valuationp.137
CabooseBuilt late 1880sOnce on E5 by the yard office; later displayed at Sewickley Riverfront Parkp.46, p.137

Other identity details: green paint and a round P&OV herald (p.139); green crew hats (p.105); radio 161.160 MHz listed as P&OV General (p.94); a modeler's "what if" 50-foot P&OV boxcar exists (p.4).

Crew roles seen in the blog:

Still unknown

Sources